• In early 2009. With careful selection of sites began the project development for designing data centers in the Republic of Croatia – good seismic zone, the lack of flood threat, sufficient distance from the military or chemical plants, etc., and a detailed discussion of all the conditions and details, according to the Uptime Institute classification of the quality of the data center.
  • In early 2012 The agreement was concluded with Nexus FGS fund where as the financier of the project the Fund for Economic Cooperation appeared exclusively through domestic capital with a sizeable percentage of the state capital. In this period the location was selected for the future data center in Jastrebarsko where there was a basic skeleton for future data center.
  • In late April 2012 began intensive construction work which ended in late October with testing infrastructure and training staff to work in the future Tier 3 level data center thus securing the start of the commercial business for Podatkovni centar Križ data center in Jastrebarsko in the beginning of November 2012.
  • Throughout the 2012 Podatkovni centar Križ data center team slowly filled in, performing all the preparations for the opening of the first data center Tier 3 levels in the region.